- Title or Description
- Cost of Travellers - Selkirk (2)
- FOI Number
- 286
- Date Received
- 18/03/2022
- Type of Request
- FOI
- Request or Question
- under the Freedom of Information Act to ask what the cost of the works being carried out in Selkirk at the old railway crossing / former Ettrick and Yarrow Spinners ground in Selkirk for the "temporary" travellers site which I understand is to accommodate the travellers until 30/6/22.
- Response
-
* Initial Site Investigation Works - £2,054.50* External Design Costs (Electric and Water) - £1,360* Advance Tree Felling and Vegetation Clearance - £4,000* Phase 1 Preliminary Risk Assessment - £600
* Phase 2 Site Investigation Works – Outturn Cost TBC but circa £20k
* Main Works (Aborted) – No valuation in from SB Contracts as yet.